Construction Updates / Actualizaciones de Construcción
August 12, 2026
Dear 24 Webster Neighbors and Community,
The 24 Webster Avenue project is continuing on schedule. Over the last month, the construction team has been working hard pouring the concrete foundation for the new building. The next steps will be to begin erecting the building's steel structure.
We expect steel work to begin the week of September 21st and to last 7 weeks. During this time, Everett Street will be closed 24/7 for the placement of a crane that is necessary for the steel construction. Although we did not originally anticipate closing Everett Street for this duration, closing the street will create a safer work site for both workers and pedestrians, avoid disrupting traffic flow on Webster Ave, and enable the construction team to move more quickly through this phase of the project. There will be a police detail during working hours and appropriate signage for the detour to Newton Street.
We appreciate your cooperation and understanding during this process. We know that the impacts of construction in your neighborhood can be challenging. Please reach out if you have any questions or concerns in the coming weeks.
Thank you,
Molly & the Just A Start team
_________________________________________________
Estimados vecinos de 24 Webster y miembros de la comunidad:
El proyecto de Webster Avenue, 24, avanza según lo previsto. Durante el último mes, el equipo de construcción ha trabajado intensamente en el vertido de los cimientos de hormigón del nuevo edificio. Las siguientes etapas consistirán en comenzar el montaje de la estructura de acero del edificio.
Prevemos que los trabajos con acero comiencen la semana del 21 de septiembre y se prolonguen durante 7 semanas. Durante este periodo, la calle Everett permanecerá cerrada las 24 horas del día para permitir la instalación de una grúa necesaria para el montaje de la estructura. Aunque inicialmente no habíamos previsto cerrar la calle Everett durante tanto tiempo, esta medida garantizará una mayor seguridad tanto para los trabajadores como para los peatones, evitará interrupciones en el tráfico de Webster Avenue y permitirá al equipo de construcción avanzar con mayor rapidez en esta fase del proyecto. Habrá presencia policial durante el horario laboral y se instalará la señalización adecuada para el desvío hacia Newton Street.
Agradecemos su colaboración y comprensión durante este proceso. Somos conscientes de que las obras en su vecindario pueden ocasionar molestias. No dude en ponerse en contacto con nosotros si tiene alguna pregunta o inquietud en las próximas semanas.
Gracias,
Molly y el equipo de Just A Start
July 9, 2026
Dear 24 Webster Avenue Neighbors,
This week may have noticed that there has been evening street work, as well as the closure of Everett Street. This is being done by Somerville Water and Sewer, and is unrelated to the 24 Webster Avenue project. We are continuing to work within the typical hours of 7am-6pm.
If you have any questions or concerns, please reach out.
Thank you,
Molly
_________________________________________________________
Estimados vecinos del 24 Webster Avenue,
Es posible que esta semana hayan notado trabajos en la calle durante el horario nocturno, así como el cierre de Everett Street. Estas labores están a cargo del Departamento de Agua y Alcantarillado de Somerville (Somerville Water and Sewer) y no guardan relación con el proyecto de 24 Webster Avenue. Nosotros seguimos trabajando dentro del horario habitual, de 7:00 a. m. a 6:00 p. m.
Si tienen alguna pregunta o inquietud, no duden en comunicarse con nosotros.
Gracias,
Molly
May 21, 2026
Dear 24 Webster Avenue Neighbors,
The 24 Webster project is well underway. We will begin pouring concrete for the building's foundation this week. In order to accomodate the concrete pump, you can expect Everett Street in front of the building to be closed to traffic for a few hours on a weekly basis. These street closures will likely take place on Thursdays or Fridays, and will be accompanied by a police detail.
As always, please reach out if you have any questions or concerns. Thank you!
________________________________________________________________________
Estimados vecinos del 24 Webster Avenue:
El proyecto 24 Webster avanza a buen ritmo. Esta semana comenzaremos a verter el concreto para los cimientos del edificio. Para dar cabida a la bomba de concreto, es previsible que la calle Everett —frente al edificio— permanezca cerrada al tráfico durante unas horas, una vez a la semana. Es probable que estos cierres de la calle tengan lugar los jueves o los viernes, y contarán con la presencia de un dispositivo policial.
Como siempre, no duden en ponerse en contacto con nosotros si tienen alguna pregunta o inquietud. ¡Gracias!
April 14, 2026
Hi 24 Webster Avenue Neighbors,
The installation of the vertical steel piles at 24 Webster Avenue will be completed this week. Thank you for your patience throughout this noisy and disruptive phase of the project.
You may have seen that we started installing lagging, which are horizontal wooden boards that retain soil as we excavate. Soil is being removed from the site by trucks as we dig. There will be a police detail for the trucks to ensure minimal disruption to traffic. This will continue throughout the month of April.
Please reach out if you have any questions or concerns. Thank you.
__________________________________________________________________________________
Hola, vecinos del 24 de Webster Avenue:
La instalación de los pilotes verticales de acero en el 24 de Webster Avenue finalizará esta semana. Les agradecemos su paciencia a lo largo de esta fase del proyecto, la cual ha resultado ruidosa y ha generado algunas molestias.
Es posible que hayan observado que hemos comenzado a instalar el entablado de contención; se trata de tablas de madera horizontales cuya función es retener el suelo a medida que realizamos las excavaciones. A medida que avanzamos con la excavación, se está retirando la tierra del lugar mediante camiones. Contaremos con presencia policial para regular el tránsito de los camiones y garantizar que las interrupciones al tráfico sean mínimas. Esta operación continuará durante todo el mes de abril.
Por favor, no duden en ponerse en contacto con nosotros si tienen alguna pregunta o inquietud. Gracias.
March 10th, 2026
Dear 24 Webster Ave Neighbors,
I am writing with an update on what to expect for the construction at 24 Webster over the next few weeks. The next phase of work involves preparing the site for excavation by installing soldier piles. You will begin to see some large equipment, such as a crane, on site. This work will be loud and may cause some vibration, which we will be monitoring. We expect this phase of work to go through the end of March. Please reach out if you have any questions or concerns.
Thank you!
Estimados vecinos de 24 Webster Ave:
Les escribo para informarles sobre las previsiones de la construcción de 24 Webster durante las próximas semanas. La siguiente fase consiste en preparar el terreno para la excavación mediante la instalación de pilotes soldados. Comenzarán a ver equipos pesados, como una grúa, en el sitio. Este trabajo será ruidoso y podría causar vibraciones, las cuales estaremos monitoreando. Esperamos que esta fase de las obras se extienda hasta finales de marzo. Si tienen alguna pregunta o inquietud, no duden en contactarnos.
¡Gracias!
February 11th, 2026
It all begins with an idea.
Dear 24 Webster Avenue Neighbors,
I am writing to inform you that we will begin demolition of the 24 Webster Avenue building next week, Tuesday, February 17th. We expect demolition to last approximately 3 weeks. We do not expect any road closures during this time. Our General Contractor will be working diligently to mitigate dust and debris. As always, please reach out if you have any questions.
Estimados vecinos de 24 Webster Avenue:
Les escribo para informarles que comenzaremos la demolición del edificio de 24 Webster Avenue la próxima semana, Martes, el 17 de febrero. Se prevé que la demolición dure aproximadamente 3 semanas. No se prevén cierres de carreteras durante este periodo. Nuestro contratista general trabajará diligentemente para mitigar el polvo y los escombros. Como siempre, no duden en contactarnos si tienen alguna pregunta.